- PROGRESS.md: hard NAT Phase A, relay cross-wiring, 588 tests - ARCHITECTURE.md: hard NAT port prediction diagram + pattern table - PRD-p2p-direct.md: Phase 8.6 split into a/b/c/d with status - PRD-hard-nat.md: Phase A done, B signal ready, effort table updated - PRD-netcheck.md: port_allocation field + probe documented Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
This commit is contained in:
@@ -1,8 +1,8 @@
|
||||
# PRD: Hard NAT Traversal (Port Prediction + Birthday Attack)
|
||||
|
||||
> Phase: Design
|
||||
> Status: Not started
|
||||
> Crate: wzp-client, wzp-proto
|
||||
> Phase: Partial implementation
|
||||
> Status: Phase A done, Phase B signal ready, C-D not started (2026-04-14)
|
||||
> Crate: wzp-client, wzp-proto, wzp-relay
|
||||
|
||||
## Problem
|
||||
|
||||
@@ -193,14 +193,14 @@ HardNatBirthdayStart {
|
||||
|
||||
## Effort Estimate
|
||||
|
||||
| Phase | Scope | Effort |
|
||||
|-------|-------|--------|
|
||||
| A | Port allocation pattern detection | 1 day |
|
||||
| B | Sequential port prediction + coordination | 2 days |
|
||||
| C | Birthday attack (256 sockets + 1024 probes) | 3 days |
|
||||
| D | Hybrid waterfall + background upgrade | 2 days |
|
||||
| Phase | Scope | Effort | Status |
|
||||
|-------|-------|--------|--------|
|
||||
| A | Port allocation pattern detection | 1 day | **Done** — `PortAllocation` enum, `detect_port_allocation()`, `classify_port_allocation()`, `predict_ports()`, 17 tests |
|
||||
| B | Sequential port prediction + coordination | 2 days | **Signal ready** — `HardNatProbe` signal + relay forwarding done. `dual_path::race()` integration pending |
|
||||
| C | Birthday attack (256 sockets + 1024 probes) | 3 days | Not started |
|
||||
| D | Hybrid waterfall + background upgrade | 2 days | Not started |
|
||||
|
||||
**Total**: ~8 days. Recommend starting with Phase A (detection) which is useful for netcheck even without the attack. Phase B (sequential prediction) covers ~40% of hard NATs with minimal complexity. Phase C (birthday) is the most complex and lowest ROI.
|
||||
**Total**: ~8 days. Phase A is done and feeds into netcheck. Phase B has signal plumbing complete — needs `dual_path::race()` integration to actually dial predicted ports. Phase C (birthday) is the most complex and lowest ROI.
|
||||
|
||||
## Success Criteria
|
||||
|
||||
|
||||